Loans for data centers
A data center is financed on contracted power. Lenders size rent per kilowatt of critical load and care first about the utility commitment, then the tenant's lease. CBRE measured 1.4%1 vacancy in primary North American markets, with more than 80%1 of capacity under construction preleased, as of H1 2026. Projects run through construction lenders, then single-asset securitizations or banks.
| SASB and large-loan share of private-label CMBS issuance, January to September 2026 (CRED iQ) | 76%5 |
|---|---|
| Median senior AAA spread, fixed-rate SASB CMBS excluding data centers, mid-October 2026 (Trepp) | 133 bps7 |
| HVCRE equity test for bank construction loans | 15% of appraised as-completed value4 |
Programs that lend on it
Not ranked by price: only some of these programs have a published spread that applies here.
| Program | Indicative rate | Leverage benchmark | Min DSCR | Recourse |
|---|---|---|---|---|
| Commercial construction loan | Deal by deal | Set deal by deal | Not published | Full recourse |
| Bank commercial mortgage | Deal by deal | 85%8 (bank supervisory ceiling) | Not published | Full recourse |
| Life insurance company loan | 6.09 to 7.14% | Set deal by deal | Not published | Non-recourse (standard carve-outs) |
| CMBS conduit loans | 6.48 to 7.14% | Set deal by deal | Not published | Non-recourse (standard carve-outs) |
| Debt fund and mortgage REIT loans | Deal by deal, this index does not cover this asset | Set deal by deal | Not published | Deal by deal |
| Owner-occupied commercial mortgage (SBA 504, 7(a), bank) | Deal by deal | Set deal by deal | 1.15x6 | Full recourse |
Layers that can sit on or around the senior loan here: Mezzanine, Pref equity and SASB.
Programs that are out or unconfirmed
| Fannie Mae, Freddie Mac and FHA multifamily loans | Residential rental programs only. |
|---|
National data: data centers
NAICS 518210 is computing and hosting businesses, most of which do not own a data center.
SBA 7(a) loans, FY2022 to FY2026
Loans to operating businesses under NAICS 518210, not investor loans. Real estate financed under SBA must be owner-occupied, and a 7(a) loan may fund working capital or equipment instead. FY2026 runs through June 30, 2026.
| Loans approved | 426 |
|---|---|
| Total approved | $217.1 million |
| Median loan | $200,000 |
| Middle half of loans | $89,250 to $414,300 |
| Median term | 120 months (10 years) |
| Loans of 20 years or more (these generally carry real estate) | 10 (2.3%) |
| Median size of those loans | $537,600 |
| Median initial rate, variable-rate loans, FY2024 to FY2026 | 11.00% |
| Median initial rate, fixed-rate loans, FY2024 to FY2026 | 8.25% |
| Startups (two years old or less) | 21.2% |
| Change in yearly approvals, FY2022 to FY2025 | +24% |
SBA 504 loans, FY2022 to FY2026
Owner-occupied projects only. Amounts are the SBA-backed second lien.
| Loans approved | 19 |
|---|---|
| Total SBA-backed debentures | $19.6 million |
| Median debenture | $648,000 |
| Middle half of debentures | $352,500 to $1,367,500 |
| Median first-lien bank loan alongside it | $780,000 |
| Median term | 300 months (25 years) |
| Startups (two years old or less) | 0.0% |
| Charged off, among resolved loans (approvals FY2010 onward) | 0.0% of 51 |
Source: SBA 7(a) and 504 FOIA loan files, as of June 30, 2026. Charge-off shares exclude active loans and are not default rates.
Securitized CMBS loans
Covers loans in SEC-registered pooled CMBS trusts only, not the wider lending market. Matched by property code 98 (other) or IN or OF, property name indicates a data center.
| Live loans | 7 |
|---|---|
| Balance outstanding | $220.3 million |
| Median balance | $13.0 million |
| Median reported occupancy | 100% |
| Median reported DSCR | 2.42x |
Source: SEC ABS-EE loan tapes, reporting period 2026-10.
Businesses in this industry
| Employer establishments | 18,544 |
|---|---|
| States and DC reporting | 51 |
Source: Census County Business Patterns, 2023. Counts operating businesses with employees, not buildings.
Power is the collateral
Data centers are priced by critical IT load: the kilowatts the tenant’s servers can draw, after cooling and losses. Building area is close to irrelevant.
A lender’s first question is therefore not who the tenant is. It is: has the utility committed to delivering this much power, on this schedule, in writing?
| Stage of power certainty | What exists | Financing it attracts |
|---|---|---|
| Speculative land with a utility inquiry | Land, a request in the queue | Equity, preferred equity, rarely debt |
| Load study complete | Utility has modeled capacity and cost | Land or pre-development debt at a modest basis, often with recourse |
| Executed service or interconnection agreement | Contractual delivery date, with construction deposits | Construction discussions become real |
| Substation or transmission work under way | Physical progress | Larger bank clubs, private credit |
| Energized, with lease commenced | Income | Permanent debt, SASB, bank term loan |
A long queue in a power-constrained market is why a site with a signed utility agreement can be worth many multiples of an adjacent site that lacks one, even when the land is identical. Lenders are skeptical of the phrases “power available” and “utility will serve” until they see the document. Terms that deserve a lawyer’s reading include the delivery date remedies, the customer’s minimum take obligations, security deposits and whether the agreement can be assigned to a lender on foreclosure.
How income is underwritten
The contract is the income. The key measure is rent per kilowatt per month against the critical load being leased. Asking rents in the primary markets rose across deployment sizes in the first half of 2026 (CBRE), but rates vary so much by market, size and structure that we do not publish a national figure.
- Wholesale versus retail colocation. Large single-tenant, long-term leases are close to net leases of a powered building. Retail colocation sells small deployments to many customers, adds services and looks more like an operating business, so it is underwritten more like one.
- Lease structure. Whether power is passed through at cost, or included. Metered power pass-through leaves the landlord out of the energy price; a fixed-power structure puts it on the landlord.
- Lease term and options. Long initial terms with a hyperscale tenant let a lender amortize meaningfully. Watch early termination rights tied to delivery dates.
- Tenant and guarantor. Who is actually on the lease? A special purpose subsidiary without a parent guaranty is a different credit from the parent. Newer AI-focused tenants may be earlier in their credit life than a large cloud company. This is the current focal point of lender scrutiny.
- Delivery conditions. Tenant termination rights for missed delivery dates, with liquidated damages. A late power date can cost the landlord the lease.
- Service level agreements. Rent credits for downtime. In a heavily loaded building, a large outage can be a material credit against income.
Power usage effectiveness (PUE) is useful as a measure of efficiency, and it matters more when the landlord carries energy cost. Higher densities from liquid cooling can reduce or increase the useful life of a building, depending on whether the plant can be adapted.
The building is a machine with a short life inside a long shell
Three layers age at different speeds, and lenders try to value them separately.
| Layer | Typical components | Lender’s view |
|---|---|---|
| Land and shell | Site, structure, security | Long life; alternate use possible only if power stays |
| Mechanical and electrical plant | Substation, switchgear, UPS, generators, chillers, cooling distribution | Very expensive, and reserves are needed for replacement |
| Tenant’s IT equipment | Servers, accelerators, networking | Not the landlord’s collateral, and quickly obsolete |
A hall designed for one density may need major rework for high-density liquid-cooled deployments. Uptime Institute tier ratings describe resilience design, and the rating is a design or construction certification rather than a performance guarantee. Ask which certification was actually issued.
How a data center construction loan really works
A data center draw schedule looks nothing like an apartment build. A large share of the budget goes to long-lead electrical and cooling equipment that must be ordered and paid for long before the building is usable. Lenders therefore focus on the following.
Deposits on equipment. Transformers, switchgear and generators can need large payments years ahead of delivery. A lender may fund those deposits only with title or a bailment agreement and an assignable purchase contract. Otherwise it is funding an unsecured claim against a manufacturer.
The lender’s engineer. Expect an independent engineer to review design, schedule and commissioning. The final tests before a hall is released to a tenant are integrated systems tests, and they drive the rent start date.
Phased delivery. Campuses open hall by hall. Loans fund against each phase, and each phase has its own lease commencement, which requires its own release mechanics if some tenants arrive late.
Completion support. Sponsors are usually asked for a completion guaranty and a carry guaranty. Ask how those guaranties burn off, and how a delay caused by the utility is treated, since neither the contractor nor the sponsor controls it.
Permits and environmental
- Backup generators. Banks of diesel generators can make a campus a major air emissions source. Federal rules limit non-emergency operation of emergency engines to 50 hours per calendar year, counted within a 100-hour annual limit that also covers maintenance and testing2, and states may set stricter hours or require a major source permit. Demand response programs that run generators outside true emergencies need careful legal review.
- Fuel storage. Generator diesel tanks can trigger aboveground plan requirements at more than 1,320 gallons of aboveground oil storage, counting containers of 55 gallons or more3, as well as state tank rules.
- Water. Evaporative cooling depends on water rights or utility agreements, and water use is now a common local approval issue.
- Zoning and community opposition. Moratoria and new special-use processes are appearing. A site with an entitlement in hand is much stronger than one that expects to obtain it.
- Grid policy. Large-load tariffs and co-location rules are moving at utilities and at federal and state regulators. Ask counsel to check the current tariff on the date of the loan commitment.
- Noise and generators. Often the actual cause of neighbor disputes.
Which programs fit
- Construction lenders: banks in clubs for large projects, private credit for the rest. Bank-held loans face HVCRE rules at 15% of appraised as-completed value.
- SASB: the common take-out for large stabilized assets or portfolios with strong leases. SASB and large-loan deals made up 76%5 of private-label CMBS issuance from January to September 2026, across all property types.
- Conduit CMBS: only for smaller stabilized assets. The national table on this page shows the few data center loans we could identify on SEC ABS-EE tapes. Those cover securitized loans only, and a private 144A single-borrower deal does not appear on them, so the table misses most of the market.
- Life companies: selective, usually with a long lease to a top credit.
- Debt funds, mezzanine and preferred equity: fill the gap between senior proceeds and total cost.
- Bank term loans: for smaller edge and enterprise facilities.
- SBA through an owner-occupied lender: small hosting companies only.
Refused: agency and FHA, which are residential or healthcare programs.
Value and exit
Three questions determine what the asset will be worth.
- Does the power stay with the property? The utility agreement should run with the land or be assignable. Without it, the shell is a warehouse.
- Is the plant fit for the next tenant’s density? A site that can be upgraded will resell far better than one that cannot.
- Who has the renewal? A big tenant that has invested heavily in its own equipment has a strong reason to renew, and also the leverage to negotiate.
Going concern and real estate are separate in retail colocation, where customer contracts, cross-connect revenue and staff form a business. A wholesale asset is closer to pure real estate. Appraisers split value between land, improvements and contract income, and a lender will read the split.
The risk the market argues about is oversupply: whether AI-driven demand will hold through the terms being financed now. Current data shows very tight conditions, but the leases being signed will be tested over many years. A lender’s stress test should include a renewal at a lower rate and a higher reinvestment cost, not just vacancy.
Illustration: what a late utility costs
An illustration, not a quote. Assume a 12 MW single-tenant project with a cost of $12,000,000 per MW, or $144,000,000. Rent is an assumed $105 per kW per month, net of power. A 65% loan to cost is $93,600,000 at an assumed 8.00% interest-only rate.
| Measure | Result |
|---|---|
| Annual rent: 12,000 kW x $105 x 12 | $15,120,000 |
| NOI at 96% of rent | $14,515,200 |
| Yield on cost | 10.08% |
| Annual interest on the full loan | $7,488,000 |
| Debt yield on NOI | 15.5% |
| Interest coverage | 1.94x |
These numbers look comfortable until the power date moves. A six-month delay in energization, fully drawn, adds $3,744,000 of interest with no rent. If the tenant holds a termination right after a certain delay, the risk becomes the whole lease. That is why lenders ask for a delivery contingency, an interest reserve sized for delay and the tenant’s remedies in writing, and why blended capital can get expensive fast.
Red flags
- “Utility will serve” letters without a load study or an executed agreement.
- Delivery dates in a lease that are earlier than the utility’s commitment.
- A tenant SPE with no parent guarantee, or a young tenant with short-term funding.
- Generators permitted only for emergencies and marketed for grid revenue.
- A site near community opposition, where entitlements could be challenged.
- A design density that the current cooling plant cannot serve.
- A contract rent at the top of the market with no comparable renewal evidence.
- Long-lead equipment (transformers, switchgear) that is not yet ordered, on a schedule that assumes it is.
Documents to assemble
- Utility agreements, load study, tariff and schedule of deposits
- Lease or letter of intent, with delivery dates, termination and SLA terms, and guaranty
- Tenant credit package
- Design basis: critical load, density, cooling, redundancy, certification
- Construction budget, contractor agreements and long-lead procurement schedule
- Air permits, tank plans, water agreements and zoning entitlements
- Phase I, geotechnical report, survey and title
- Sponsor track record, equity source and capital stack
- Insurance plan for construction and operations
Bringing a powered site or a pre-lease? Get financing terms by sending the utility agreement first; every lender will ask to see it.
Similar property types
Questions people ask
How is data center vacancy measured?
CBRE reports 1.4%1 for eight primary North American markets and lists available capacity in megawatts, but its release does not define vacancy. Data center space is leased by power, so a building can have open floors and no available power and be full for practical purposes. Ask any source how it measures the figure.
Can an SBA loan finance a data center?
For a small operator that occupies the building, possibly. SBA rules require the business to occupy at least 51% of rentable space of an existing building, and the loan caps are far below hyperscale cost. The SBA figures on this page describe small hosting businesses, most of which own no data center.
Does GPU equipment count as collateral for the real estate loan?
Generally not. Servers and accelerators usually belong to the tenant and turn over quickly. Equipment finance for them is a separate market, with different lenders, shorter terms and much faster depreciation. A real estate loan covers land, shell and the building's electrical and cooling plant.
Related
Sources
- CBRE, North America Data Center Trends H1 2026 press release, as of June 30, 2026
- 40 CFR 60.4211(f), eCFR, as of November 4, 2026
- 40 CFR 112.1(d)(2)(ii), eCFR, as of November 4, 2026
- 12 CFR 324.2, definition of HVCRE exposure (eCFR), as of October 29, 2026
- CRED iQ, The Power of One: Why SASB Outruns Conduits 3 to 1 (Oct 22, 2026), as of September 30, 2026
- SBA SOP 50 10 8.1, Lender and Development Company Loan Programs (effective Oct 1, 2026), as of October 1, 2026
- Trepp, Data Center CMBS Spreads Widen as the Rest of the Market Holds Steady (Oct 27, 2026), as of October 16, 2026
- eCFR, 12 CFR Part 365 Appendix A (Interagency Guidelines for Real Estate Lending Policies), as of November 26, 2021
- 40 CFR Part 60 Subpart IIII, stationary compression ignition engines, as of November 2026
- CBRE North America Data Center Trends H1 2026, as of August 2026
- Uptime Institute Tier Classification System, as of November 2026
- SBA 7(a) and 504 FOIA loan files, as of June 30, 2026